F-D Road Project (Upgrading of Fufuya-Dodoma (70.9Km) to Bitumen Standard)

Completed section of the Project

Completed section of the Project

Located in central Dodoma, capital of Tanzania, the F-D Road Project is Section III of the Iringa-Dodoma Road Upgrading Project, which extends from Fufuya to Dodoma with a total length of 70.9km. The Project is designed to upgrade the existing gravel road to asphalt road. It was commenced on March 15, 2011 with the construction duration of 33.3 months.